Detailed Project Report (Intensive Block wise)

Intensive Block wise % of DPR Upload in connection with Total Watershed.
Intensive Block wise status on Watershed and DPR
Intensive Block wise Watershed vis-a-vis Detailed Project Report Upload
Sl. District Name Block Name (Intensive) Total No. of watershed Total No. of watershed convenient to work No.of Watershed Where DPR already uploaded No.of Watershed DPR yet to be upload % of performance
1 PURULIA BAGMUNDI 90 88 88 0 100.00
2 JHARGRAM BINPUR-I 62 62 62 0 100.00
3 JHARGRAM BINPUR-II 86 86 86 0 100.00
4 BANKURA GANGAJAL GHATI 59 59 47 12 79.66
5 BANKURA HIRBANDH 24 24 24 0 100.00
6 PURULIA HURA 56 56 56 0 100.00
7 BANKURA INDPUR 37 37 36 1 97.30
8 PURULIA JHALDA-II 28 28 28 0 100.00
9 JHARGRAM JHARGRAM 80 77 77 0 100.00
10 PASCHIM BARDHAMAN KANKSA 39 27 27 0 100.00
11 PURULIA MANBAZAR-I 43 43 43 0 100.00
12 JHARGRAM NAYAGRAM 70 69 62 7 89.86
13 BIRBHUM RAJNAGAR 33 33 28 5 84.85
14 BANKURA RANIBUNDH 50 50 45 5 90.00
TOTAL 757 739 709 30 93.66